All the data is already in the excel template. Only have to complete part 2a and 2b. 1 and 2c, 2d are already done
1 paragraphs(doesnt have to be a long paragraph for question a)
Based on PM Analysis results, answer the following questions:
a) What is the expected project completion time? Is the time estimation subject to a lot
of variations?
b) If you are more conservative, and you want to find out the due date by which the
project can be completed with a probability of 95%, what will be the due date?
Include the computation steps (either in Excel using Excel functions or in the essay if
you do manual calculations). The z-score corresponding to 95% is 1.65.